How to track change orders so none go unbilled

Set up a simple change order log in Google Sheets so every client request gets priced, signed and billed before the work starts.

By Orion Jones, Westward

Put every change in one shared log, and make a rule that no work starts until the log shows a price and a signature. A Google Sheet is enough to run this. Most money lost on change orders is not the big ones. It is the small ones said out loud on site.

Why change orders go unbilled

The homeowner asks on a walkthrough to move an outlet. Your framer nods. Nobody writes it down. Three weeks later the electrician sends an extra bill, and you either eat it or have an awkward talk with the client.

Each request passes through several people: the homeowner, you, your superintendent, the sub and your bookkeeper. If it is not written down at the first step, it can disappear at any of the next four. The fix is not more discipline. The fix is one place where every request lands the same day.

Step 1: Build the log

Make a Google Sheet with one row per change. Use these columns:

  • Change order number (CO-001, CO-002 and so on)
  • Job name
  • Date requested
  • Who asked (homeowner, architect, you)
  • Plain description of the change
  • Your cost
  • Price to the client, with your markup
  • Days added to the schedule
  • Status (requested, priced, sent, signed, billed)
  • Date signed
  • Invoice number

Turn Status into a dropdown so nobody types it differently. Then add a filter that shows every row not marked billed. That filtered view is your leak detector.

Step 2: Set one rule and say it out loud

The rule is simple. No work starts on a change until the status says signed. Put it in your contract language, say it at the kickoff meeting, and tell every sub and your superintendent.

Homeowners accept this when you frame it as protection for them. They see the exact price before they commit, and they get a clean record at the end of the build. Most arguments over final cost come from people remembering a conversation differently.

Step 3: Make capturing the request take one minute

If logging a change is a chore, your superintendent will skip it. Build a Google Form they can open from a phone home screen. Ask for four things: the job, what was asked, who asked, and a photo. Every answer lands as a new row in your sheet with the status set to requested.

A voice note works too. Your super records 20 seconds in the truck, and you or your office manager types it into the sheet. The point is that the request is recorded within the same day.

Step 4: Price it and send it within two days

A change that sits unpriced is a change someone will start anyway. Make a change order template in Google Docs or in your accounting tool. Keep it to one page:

  • What is changing, in plain words
  • The price
  • Days added to the schedule
  • The new contract total
  • A signature line

Send it for signature with DocuSign or whatever your clients already use. When it comes back, update the sheet to signed and add the date. When you invoice it, mark it billed and add the invoice number from QuickBooks.

Step 5: Review the log every Friday

Spend 15 minutes on Friday with the log filtered to anything not billed. Look for two things. First, rows stuck at requested for more than three days. Second, rows marked signed that have no invoice number yet.

Here is why this is worth 15 minutes. If you miss one 600 dollar change on each house you build, that is 600 dollars gone per project, and it costs you nothing but a missing line in a spreadsheet. Plug in your own numbers and see what a single missed change costs you across a year.

What to do yourself and what is worth paying for

Do these yourself: build the sheet, set up the Google Form, write the one rule, and run the Friday review. You can have all of it working in an afternoon, and it will catch most of the leaks.

Pay someone when the manual steps start to pile up. That usually means these jobs:

  • Turning a form entry into a finished change order document with the right job, price and contract total filled in
  • Sending it for signature and updating the log when it comes back
  • Creating the draft invoice in QuickBooks when the change is signed
  • Alerting you when a change has been sitting unpriced for more than two days

This is worth it if you run several jobs at once and your office manager is retyping the same details into three places. Each retype is another chance for a typo or a missed line.

Next step

If you want the log, the form, the signature and the invoice to connect without anyone retyping, look at custom builds for your business. Or talk it through with us and we will look at how your change orders move today.