How to Track Change Orders on a Luxury Renovation
Set up one Google Sheet that logs every change order, gets client sign off, and shows the running total, so no extra work goes unbilled.
By Orion Jones, Westward
Track change orders in one shared log where every request gets a number, a price, a schedule impact, and a client signature before the work starts. A Google Sheet plus a simple signature step is enough. The goal is that no extra work gets done on a verbal okay.
On luxury projects, changes are normal. A client sees the framed room and wants the window bigger, the stone swapped, or the lighting redone. Each change is fair to ask for. The trouble starts when nobody writes down what it costs, and the final bill surprises everyone.
Where money leaks
Most unbilled work comes from small things said on site. The client mentions a change to the foreman, the foreman says sure, and the crew does it. Nobody tells the office. Three weeks later it is lost.
There is a second leak. A change has a ripple effect on the schedule, such as a longer lead time on a new fixture, and no one adds it up. The client thinks the move-in date has not changed. It has.
Both leaks are fixed by the same habit: nothing happens until it is written down and approved.
Step 1: Build the change order log
Open Google Sheets and create one file per project, or one file with a tab per project. Use these columns:
- Change order number, such as CO-001
- Date requested
- Who asked, and how (site visit, email, text)
- Description of the change
- Cost to the client
- Added or removed days on the schedule
- Status: requested, priced, sent, approved, done, billed
- Date approved
- Link to the signed document
Add a total row at the bottom that sums approved costs. Next to it, show the original contract amount and the new contract total. Clients like seeing that math, and so do you.
Step 2: Make one template for the document
The sheet is for you. The client needs a clean one page document. Make a template with the project name, the change number, a plain description, the price, the schedule impact, and a line that says work will not begin until it is signed.
Keep the wording short. If the change is a lot more complex, attach a sketch or a photo of the spot.
Send it for signature through DocuSign or a similar tool, or even a PDF the client signs and returns. A tapped okay in a text message is better than nothing, but a signature is easier to rely on later.
Step 3: Set the on site rule
This is the part that makes the system work. Tell everyone on the crew the same thing: if a client asks for a change, the answer is, Great, let me get you a price. That is all they say.
Then they send a quick note to the office. It can be a text, a voice memo, or a form on their phone. The office logs it, prices it, and sends the document.
You can say this kindly to the client up front. In your kickoff meeting, explain that you track every change so they always know the real number. Luxury clients tend to appreciate clarity about money.
Step 4: Review weekly
Once a week, sort the sheet by status. Look for anything marked requested or priced for more than a few days. Those are changes sitting without an answer, and work may already be happening on them.
Then compare approved changes to what you actually invoiced. If a change is marked done but not billed, bill it now. This weekly check takes about 10 minutes if the log is current, and one missed line item on a large job can easily cost more than that.
What to do yourself and what is worth paying for
Do this yourself:
- Build the sheet and the one page template
- Write the on site rule and share it with your foremen
- Start a log on your next job, not your whole backlog
These are worth paying someone to set up:
- A simple phone form for crews that adds a request straight to the log, so nothing depends on someone texting the office
- Automatic creation of the change document from the log row, with the numbers filled in
- A link from approved changes to QuickBooks, so the invoice includes them without retyping
The phone form is the most useful of these, because the real gap is between the site and the office. If you keep retyping the same details into a sheet, a document and an invoice, that is three places for an error.