· For pool builders
How to handle pool change orders without a payment fight
Use a one-page change order, a signature before work starts and a simple tracking sheet, so extras on a pool build get approved and paid.
By Orion Jones, Westward
Get every change in writing, with a price and a signature, before your crew does the work. A one-page change order that states what changed, what it costs and how it moves the schedule prevents most end-of-job arguments. Do it the same way every time, even for small changes.
Where pool change orders come from
Pool jobs change after the contract is signed more than most builds. Rock or a high water table shows up during the dig. The customer decides on extra tile, a spa, new lighting or a longer sun shelf. The equipment pad moves because of a utility line or a neighbor's fence. An inspector asks for something. Each one is a fair reason to change the price, but only if the customer agreed to it first.
The fights happen at final payment. The customer remembers a casual yes on site. You remember an extra that cost real money. With nothing written, you both feel right.
Build the one-page change order
Make a Google Doc or a Google Form with these fields:
- Job name, address and date
- Change order number (1, 2, 3 for that job)
- What is changing, in plain words
- Why it is changing (customer request, site condition, inspection)
- Price added or removed
- New contract total
- Effect on schedule, in days, or none
- Signature lines for the customer and for you
Keep the language short. One change per order, so a customer can approve the spa without also approving something they have not thought about.
If the change is a site surprise like rock, add a line showing how you priced it so the customer sees it is not a random number.
Get it signed before work starts
Send the change order through DocuSign, or as a PDF the customer can sign on their phone. A text that says yes, go ahead is better than nothing, but a signature on the actual document is what holds up. Tell the crew lead that no extra work starts until a signed change order exists. That one rule does most of the work.
For small items you may want a looser rule, such as a dollar amount under which your foreman can say yes. Decide that ahead of time and write it into your contract, so you are not making it up on site.
Track them in one sheet
Keep a Google Sheet with one row per change order. Columns: job, number, description, amount, date sent, date signed, invoiced yes or no, paid yes or no.
Each week, filter for rows that are sent but not signed, and signed but not invoiced. Those two filters show you where money is leaking. If you use QuickBooks, create the invoice or update the progress invoice the same day the change is signed, so the work and the billing never drift apart.
Also update your draw schedule. If a change moves the contract total, the remaining payments change too. Write down the new numbers so the customer is not surprised when the next invoice looks different.
A quick check on time: if you currently spend 20 minutes per change digging through texts to rebuild what was agreed, and you have 4 changes on a job, that is over an hour per job. A template takes a couple of minutes to fill in.
What to do yourself and what is worth paying for
Do it yourself: the form, the sheet and the no-signature-no-work rule. All three are free or cheap and you can start on your next job.
Pay for setup when the process gets heavy. For example, your foreman fills a form on a phone on site, the customer gets a signing link right away, the signed copy files itself in the job folder, and the contract total and your accounting software update on their own. That connects forms, signatures, folders and QuickBooks, which is the kind of glue work that is tedious to build and easy to break. Have it built once, around your real contract language.
Separately, have your attorney or a contract expert look at your change order clause. Software can move the paper, but it cannot tell you what your contract should say.